It is noted that this situation did not stop construction at the facilities. By the end of this year, it is planned to open traffic on new bridges.
Kyiv. Ukraine. Ukraine Gate – June 30, 2021 – Reports
After arriving at the construction site in the area of Krivoy Bukhta, the crane quickly began work. Yesterday, June 29, Zakhary completed the installation of the third section of the upper part of the cable-stayed bridge, which connects the island of Khortitsa with the left bank.
The 685-ton section connected the pylon with the approaches to the bridge from the Coastal Railway.
The Road Service noted that in the near future the bridge builders are planning to prepare for installation a span from the pylon towards the Khortytsya island. First, temporary support will be installed there, and then the next section of the superstructure, which is now assembled and located on the roll-out pier of the construction site in the area of Kryvyi Bay.